Project Meeting 2021.04.29
Ben Stabler edited this page Apr 29, 2021
·
8 revisions
Task 1 Project Management (milestone)
- Bench IRFP released for phase 6b work
- Let's get started scoping phase 7 now
- Meeting with AMPO tomorrow to talk through some admin issues
- Plan to circulate final MOU
Task 2 Complete Estimation Mode (milestone)
- Done
Task 3 Telecommute Model in Cooperation with SEMCOG (milestone)
- Finalized the telecommute model doc
Task 4 Transit Pass Ownership Model in Cooperation with SEMCOG (milestone)
- Need to create example treatments in mode choice next and update/finalize transit pass model design doc
Task 5 Performance Enhancements (milestone)
- Done
Task 6 Prototype multiple models test system (milestone)
- Done
Task 7 Input checking and error handling and pipeline improvements (milestone)
- Jeff working on improved RAM/chunking settings #406
Task 8 Maintenance and Support (milestone)
- Done